24" thick components


Project Start Date: Mon 5/28/01
Project Finish Date: Wed 11/7/01

Note that this schedule is allowing and not pushed.  The time periods allowed are based on time used in the past when delays occured in the periods of time expected.  Casting time is based on 1 casting per day with a total of 8 new molds with 3 extra end panels and 6 extra side panels.

Mold Making and Casting Schedule for new components

Resources and AssignmentsStartFinish
Sign agreement & depositSat 6/2/01Sat 6/2/01
TDAC mold design laser partsMon 6/4/01Tue 6/12/01
Oneal programming laser partsWed 6/13/01Tue 6/26/01
Oneal cutting & machiningWed 6/27/01Thu 8/23/01
Mold Assembly (allow 2 days each)Fri 8/24/01Thu 9/20/01
Casting 15 F_30, 3 LC_30 , 3 RC_30, 3 SE_30Fri 9/21/01Tue 9/25/01
Casting 36 F_30, 6 LC_30 , 6 RC_30,Wed 9/26/01Wed 10/3/01
Casting 199 F_30Thu 10/4/01Wed 11/7/01