Project Start Date: Mon 5/28/01
Project Finish Date: Wed 11/7/01
Note that this schedule is allowing and not pushed. The time periods allowed are based on time used in the past when delays occured in the periods of time expected. Casting time is based on 1 casting per day with a total of 8 new molds with 3 extra end panels and 6 extra side panels.
| Sign agreement & deposit | ||
| TDAC mold design laser parts | ||
| Oneal programming laser parts | ||
| Oneal cutting & machining | ||
| Mold Assembly (allow 2 days each) | ||
| Casting 15 F_30, 3 LC_30 , 3 RC_30, 3 SE_30 | ||
| Casting 36 F_30, 6 LC_30 , 6 RC_30, | ||
| Casting 199 F_30 |